Summer disruptions to impact Upper James and Rymal area

This article, from April 26, has details on upcoming traffic disruptions in the southern portion of Ward 8.

Hello Ward 8 Neighbours,

A number of projects will be happening along the southern portion of Upper James Street, reducing the laneway to 1-lane in each direction at various points this summer.

Those who use the roadway for work or live in the area should take note of when disruptions will be taking place.

For more details, please continue reading below…

The upcoming disruptions are in relation to a number of projects.

An ongoing upgrade to the HC018 Pumping Station and Sanitary Force Main installation are two projects which will betaking place. Because of that work, Asset Management will be lining the downstream section of sanitary sewer, ending at Delta Dr.

For the work to be completed, an extensive Bypass pumping will be required, which will involve temporary and longer-term durations or detours to allow for the burial of bypass piping.

Below you’ll be able to see upcoming impacts to arterial and side roads between May and September of 2021.

These times are a general estimation for the moment.

Bypass Crossing @ Upper James & Alderlea Ave;

  • To be completed in 2 phases to allow for 1 lane of traffic in both directions
  • Duration : 2 days
  • Construction Schedule : Week of May 3, 2021

Bypass Crossing @ Aldercrest Ave

  • Temporary closure to allow for burial of bypass piping
  • Duration : 1 day
  • Construction Schedule : Week of May 3, 2021

Bypass Crossing @ Seneca Ave

  • Temporary closure to allow for burial of bypass piping
  • Duration : 1 day
  • Construction Schedule : Week of May 3, 2021

Springside Dr : Closure between Alderlea & 128 Springside Dr

  • Extended road closure for bypass installation, staging and liner installation
  • Duration : June 14 – Sept 30, 2021
  • Construction Schedule : June 14, 2021

Springside Dr : Temp Road Closure between 128 Springside Dr & Rymal Rd

  • Temporary road closure to allow for excavations and burial of bypass piping along west side of Springside Dr
  • Duration : June 14 – Sept 30, 2021
  • Construction Schedule : June 14, 2021

Bypass Crossing @ Rymal Rd & Springside Dr

  • Temporary road closure to allow for excavations and burial of bypass piping across Rymal Rd
    • To be completed in 2 phases to allow 1 lane of traffic in each direction
  • Duration : 2 days
  • Construction Schedule : June 21 – July 1, 2021
  • Removal Schedule : Week of Sept 13, 2021

Bypass crossing along Atessa Dr (Rymal Rd to Dicenzo)

  • Temporary road closure to allow for excavations and burial of bypass piping along west side of Atessa Dr
  • Duration : 5 days
  • Construction Schedule : June 21 – July 1, 2021
  • Removal Schedule : Week of Sept 13, 2021

Questions or concerns?